8.3
TIMER VERIFICATION.
8.3.1.
Settings:
8.3.1.1.
Set the Main and Topping Charge Current Selectors to zero.
8.3.1.2.
Set both Time Selectors to zero.
8.3.1.3.
Set the Timer Speed Switch to the test (center) position.
8.3.2.
NOTE: Current and voltage readings must remain at zero during the following
tests. If voltage starts to rise, which may lead to voltage a fault, verify that the
current selectors are completely at zero.
8.3.3.
Start the unit by depressing the two rate charge selector.
8.3.3.1.
The unit will go immediately into Cycle End.
8.3.3.2.
Reset.
8.3.4.
Set the total time to 01 and start.
8.3.4.1.
Unit will start in main charge and immediately transfer to topping,
going into cycle end after one second.
8.3.4.2.
Reset.
8.3.5.
Set the main time to 1, total time to 02 and start.
8.3.5.1.
The unit will start in the main mode, transfer to topping after one
second and go into cycle end after two seconds.
8.3.5.2.
Reset.
8.3.6.
Repeat the above tests, each time advancing the main and total time selectors as
follows: 2/04, 4/08, 8/09, 9/10, 9/20, 9/40 and 9/79 (or 9/60 depending on the
type of Timer).
Summary of Contents for Supercharger 60
Page 7: ...Operator Manual Supercharger 60 R3 0 Page 7 of 62 Figure 1 Block Diagram ...
Page 20: ...Operator Manual Supercharger 60 R3 0 Page 20 of 62 Figure 2 Front Panel ...
Page 44: ...Operator Manual Supercharger 60 R3 0 Page 44 of 62 Figure 6 Meters Board Adjustments ...
Page 52: ...Operator Manual Supercharger 60 R3 0 Page 52 of 62 Figure 11 Circuit Board Sequence ...
Page 57: ...Operator Manual Supercharger 60 R3 0 Page 57 of 62 Figure 13 Location of Current Limiters ...
Page 58: ...Operator Manual Supercharger 60 R3 0 Page 58 of 62 Figure 14 Power Block Diagram ...