DEFINITY Enterprise Communication Server Release 9
Installation and Maintenance for Survivable Remote EPN
555-233-121
Issue 2
November 2000
SREPN Installation
1-7
Install the SRP cabinet
1
Install the SRP cabinet
1. Place the SRP cabinet on the floor or on top of the other Single-Carrier
Cabinets (SCC). The maximum number of stackable cabinets is 4.
NOTE:
The expansion port network (EPN) appears in this document as
either a Multicarrier Cabinet (MCC) or SCC.
Connect cabinet ground
For cabinet installation, power, and ground information, refer to the Single-Carrier
Cabinet installation procedures in
DEFINITY Made Easy
tools. The SRP needs a
dedicated power source.
Install rear panels
1. Install the rear panels and loosely thread each screw. See
page 1-8
.
2. For
unstacked
cabinets, tighten the screws securely.
For a
stack
of cabinets, allow the screws (Figure Note 4 in
page 1-8
) to remain loose. These screws are tightened when the ground
plates are installed.