1 Sensors
Page | 17
MM Application Possibilities
Figure 1.1.3.ii Mini Mk8 MM Valve Proving Diagram
Figure 1.1.3.ii shows the valve proving operation in the Mini Mk8 MM. The tests have been designed
on the Mini Mk8 MM used with block valves; a pressure drop is seen when the valves close after the
‘void to air’ and ‘void to gas’ states.
In the VPS air proving phase, after the valves close, there is a 1.5 second delay before the pressure
reading is taken.
In the VPS gas proving phase, after the valves close, there is a 1.5 second delay before the initial gas
pressure reading is taken. The reading taken after this delay must be at least 80% of this measured
static pressure.
Summary of Contents for Mk8 MM
Page 1: ...Combustion Management Systems MM APPLICATION POSSIBILITIES Technical Manual 18 12 2019...
Page 8: ...1 Sensors Page 2 MM Application Possibilities Gas Pressure Sensor...
Page 27: ...1 Sensors Page 21 MM Application Possibilities Air Pressure Sensor...
Page 32: ...1 Sensors Page 26 MM Application Possibilities Steam Pressure Sensor...
Page 36: ...1 Sensors Page 30 MM Application Possibilities Outside Temperature Sensor...
Page 37: ...1 Sensors Page 31 MM Application Possibilities Outside Temperature Module...
Page 38: ...1 Sensors Page 32 MM Application Possibilities Outside Temperature Module Wiring...
Page 42: ...2 Flame Safeguard Page 36 MM Application Possibilities 2 1 1 Interrupted Pilot Gas...
Page 43: ...2 Flame Safeguard Page 37 MM Application Possibilities 2 1 2 Interrupted Pilot Oil...
Page 46: ...2 Flame Safeguard Page 40 MM Application Possibilities IR End View Scanner...
Page 72: ...2 Flame Safeguard Page 66 MM Application Possibilities 2 9 3 Wiring...
Page 81: ...5 Intelligent Boiler Sequencing Page 75 MM Application Possibilities 5 1 3 Hot Water Example...
Page 83: ...5 Intelligent Boiler Sequencing Page 77 MM Application Possibilities 5 1 5 IBS Communications...