- 66 -
Adjust engine inlet and outlet valves (2)
x
Check fuel injectors (2)
x
Check engine protective devices
x
x
Inspect starter motor
x
x
Inspect turbocharger
x
x
Inspect waterpump
x
x
Inspection by Atlas Copco service technician
x
x
x
Generators in standby application have to be tested on a regular basis. At least once a
month the engine should run for one hour. If possible a high load (> 30%) should be
applied so that the engine reaches its operating temperature.
Maintenance schedule
Daily
50 hrs
after initial
start-up
Every 500
hours
Every 1000
hours
Every 2000
hours
Yearly
Service pak
-
2912 4412 05 or
2912 4546 05
*
-
-
!
Summary of Contents for QAS 60 Pd
Page 1: ...QAS 60 Pd S2A APP Instruction Manual for AC Generators English...
Page 2: ......
Page 111: ...111 Circuit diagrams...
Page 115: ...115...
Page 119: ...119...
Page 128: ...128...
Page 132: ...132...
Page 139: ...139...
Page 141: ......
Page 142: ...Printed in Belgium 04 2012 2954 6280 00 www atlascopco com...