FEATURES & SPECIFICATIONS
HeatNet Control V3 3.x
Page 13
The boiler has a heat demand and will not start until the programmed GPM requirement is met. In this case
the minimum flow is below the required 16 GPM so the boiler will not start. The flow proof has expired and
then enters a fault condition.
The touchscreen displays a visual flow fault, and the control will annunciate an audible fault. After ten minutes
the boiler will retry to start the pumps to achieve flow and start the boiler. If there are other boilers on the
network the Master will attempt to start one of them.
If the boiler is running it will also stop firing when the GPM falls below the settings value. The touchscreen
displays a visual flow fault, and the control will annunciate an audible alarm. If there are other boilers on the
network the Master will attempt to start one of them. After ten minutes, if the demand is still present, it will
retry to start the pumps to achieve flow. If the flow is reestablished, the boiler will attempt to start.