Installation instructions AQUAmax
®
BASIC/CLASSIC 1-75
ATB WATER GmbH, Südstraße 2, D-32457 Porta Westfalica, www.atbwater.com /
Art.-No.: 9060 0209 / Status: 17.01.2019 / Page 10 from 24
Tank Preparation
AQUAmax
®
BASIC – New Plant
AQUAmax
®
BASIC - Retrofitting
Installation Example AQUAmax
®
BASIC
,
The diagram shows a typical installation of a 3-chamber
tank with installed AQUA
max
®
. With this, the suction pipe
of the AQUA
max
®
produces the connection to the last
chamber of the primary settling stage. Here the thick
matter is separated from the influent
Cover opening at least 60 cm diameter with ventilation
openings or separate ventilation pipe.
Emergency overflow, ca. 4 x 10 cm (H x W).
So far as the danger of a back-up exists in the inlet pipeline
and this is to be avoided, the lower edge of the emergency
opening is to be planned below the lower edge of the inlet.
Close openings in the partition wall. If necessary, reseal tank
joints.
Introduce empty pipe > DN 100 for cable at any desired
position.
Inlet and outlet must project ca. 15 cm into the plant.
Coarse interceptor
and sludge store
Coarse interceptor
and sludge store
SBR aeration
Inlet
Outlet
Cover opening at least 60 cm diameter with ventilation
openings or separate ventilation pipe.
Lay inlet into 2nd chamber and seal in.
Close openings in partition wall. If required, reseal tank joints.
Introduce empty pipe > DN 100 for cable at any desired
position.
Inlet and outlet must project ca. 15 cm into the plant (if
necessary, remove old partition walls) and/or mortise spigot
free.
An emergency overflow can be planned here (see above) in
order to use the half-chamber as additional buffer with power
or pump failure, before the water reaches the outlet.
Lower edge overflow must then lie below lower edge outlet but
above H
W, max
.
Coarse interceptor
and sludge store
Inlet
Outlet
SBR aeration
CI and
sludge store