Set-up operation
EN
The installation and operation of electric locking systems in escape routes are
subject to building inspectorate regulations, which the installer and operator are
responsible for ensuring compliance with.
Before initial commissioning
1 Before commissioning an electric escape-door locking system for the first
time, a check must be carried out to ensure that all elements and their
electrical connection are correctly installed. Particular care must be taken
with regard to the elements for releasing the locking in the event of danger.
2 Have correct installation and function of the escape-door locking system
checked by technical specialists.
Important!
These instructions are standard specifications. As the use of escape route locking
systems is regulated on a national or local basis, respective local building
legislation and inspection regulations for technical systems should be observed.
Automatic system check after switching on
When the system is turned on or if there is a failure in the power supply, the
position of the internal emergency switch and the status of all control inputs are
queried automatically. The resultant system switching status is then directly
dependent on the determined parameters.
If an alarm is triggered after switching on, the cause of the alarm must be rectified
(“Removing the upper part of the housing”, page 48).
A
Set-up operation
Summary of Contents for EffEff 1340-14
Page 31: ...31 DE Technische Daten ...
Page 35: ...35 DE Checkliste Prüfung vor der Erstinbetriebnahme ...
Page 67: ...67 EN Maintenance and inspection EN ...
Page 71: ...71 EN Check list Testing before initial operation EN ...
Page 74: ...74 EN ...
Page 75: ...75 EN EN ...