33
When the installation and filling are completed, flush the system while
cold, refill, turn on the Central Heating system (S
ECTION
3) and run it
until the temperature has reached the boiler operating temperature.
The system must then be immediately flushed through.
The flushing procedure must be in line with BS 7593:1992 code of
practice for treatment of water in domestic hot water central heating
systems.
During this operation, we highly recommend the use of a central
heating flushing detergent (Fernox Superfloc or equivalent), whose
function is to dissolve any foreign matter that may be in the system.
Substances different from these could create serious problems to
the pump or other components.
The use of an inhibitor in the system such as Fernox MB-1 or
equivalent is strongly recommended to prevent corrosion (sludge)
damaging the boiler and system, following the flushing procedure..
Failure to carry out this procedure may invalidate the appliance
warranty.
For IE it is necessary to complete a “Declaration of Conformity” to
indicate compliance to I.S.813. An example of this is given in the
current edition of I.S.813. In addition it is necessary to complete the
Log Book.
15.2
Completion