Installation
Standard Installation
A “Standard Installation” is one where the gate(s) open by swinging INWARDS towards the
motor housing.
The gate hinge should be no more than 200mm from the rear of the pier/post. Side room of
350mm is required to accommodate the swing of the arms.
Refer to Pages 10 & 11 if there is restricted side room (See figure 1)
Installation Procedure
1.
Ensure that the gates swing freely and that all existing latches/pad-bolts/chains etc
are disabled or removed from the gate and gate posts.
2.
When using a 240-volt unit, The Master operator (the one containing the circuit
board) should be fitted to the gatepost nearest the power supply. Remove the cover(s)
from the operator to access the slotted fixing holes in the rear of the chassis. Bend
the tabs out and bend them back against the rear of the chassis, in this position they
act as a spacer allowing clearance for the cover(s). NOTE: Do not remove these tabs –
just bend them out and fold them to the back unless you are using the OPTIONAL
mounting plate.
3.
Position each unit on the gate-post{s} approximately 50mm from the edge of the
pier/post. The vertical position is found by locating the gate bracket. The gate
bracket is best placed where there is adequate fixing on the gate and movement of the
arms is unrestricted (See Figure 2). The gate operator may now be bolted in place.