17. INSTALL EMERGENCY PIT SWITCH
18. WIRE IN THE HERCULES II HYBRID POWER SUPPLY
PROCEDURE
Install and wire the Emergency Pit Switch.
PROCEDURE
Wire and connect the
Hercules II Hybrid
to the main power supply
INSTALL
1. Unroll the Pit Switch cable and thread through the pre-drilled hole located on the
lower side of the Lower Rail Assembly.
2. Install the Emergency Pit Switch on the Supporting Wall,
24’’
(60.96 cm) from the
ground.
3. Connect and wire the switch using the rolled-up cable below the Control Panel
using the Emergency Pit Switch Wiring Diagram.
ENSURE THAT THE BOTTOM OF THE
PIT SWITCH IS 24” (60.96 CM) ABOVE
THE GROUND.
WARNING
The
Hercules II Hybrid
Vertical Platform Lift requires a 110VAC-15 AMP grounded electrical circuit
and a GFCI protected circuit. Verify with Technical Drawings and Electrical Diagram before wiring.
Ensure to follow all local codes and regulations.
WARNING
Emergency Pit Switch
Control Panel
24
” (
60
.96 cm
)