TAS12-EDM & TAS12P-EDM Installation Instructions
Page 10
For Assistance: [email protected] +1 (909) 591-8431 PUD4005R1-0
Anchoring the Turnstile
1. Using a turnstile lid key, open the turnstile leg access
panels [Figure 4].
2. Using a 9/16" socket wrench, remove the four (4)
bolts that secure the temporary wood plate to the
turnstile. Discard the wood plate.
3. Place the turnstile in the desired location. Check
that the turnstile is level and does not rock. If the
turnstile is not level, shimming will be required before
anchoring.
Primary power terminal block and power button are
always located on the secured or internal side of the
facility. Keep this in mind when placing the turnstiles
according to project layout.
4.
Transfer four (4) anchor locations to the floor
[Figure 5].
5. Move the turnstile to the side.
6.
Using a hammer drill fitted with a 5/8” concrete bit,
drill each anchor hole to a depth of 3” (76.2mm).
7. Using a shop vac, vacuum debris from the anchor
holes before installing the anchors. If the holes are
not clear of debris, the anchors may not tighten
properly.
8. Insert anchors into the drilled holes with the threaded
ends down. If needed, use a hammer to tap the
anchors into place. Ensure that the anchors are flush
with the concrete floor [Figure 6].
9. Return the turnstile to the install location, ensuring
the anchors holes are aligned.
10. Route primary power wiring and network cable (if
using) through the appropriate conduit opening into
the turnstile. Primary power wiring will be connected
in later steps.
11. Insert anchor bolts.
12.
Using a torque wrench (ft-lbs.) and 9/16” socket,
torque the threaded rods to 20 ft.-lbs.
13. For outdoors installations, apply a thick bead of clear
RTV silicone around the base of turnstile legs to seal.
Anchoring Holes
(2 total)
Concrete Anchor
(Head and arms not shown for ease of view)
Access
Panels
Anchor
Locations
NOTE
Fig. 4
Fig. 5
Fig. 6