Fascias and Capping
10
Diagram 46
Dia. 47
With all the felt in place you can begin to fix the fascias. Start with the fascia above the door. You
will notice the holes are slightly off-set, in this install they should be closest to the top of the fascia.
Make sure the felt is folded down tight along the bottom of the roof, also line up the ends with the
ends of the soffits. The more time you take over lining these up will make a big difference to the
overall finish.
You will need to trim the felt at the corners, trim the bottom layer and overlap the top layer.
Fix in place with 40mm round head stainless steel screws.
N.B.
If you have the
optional slatted roof go to
section 11
now.
Diagram 47
AB0048