Publication 2100-IN012B-EN-P - April 2005
2-2
Installation Procedures
Figure 2.1 Height Planning Dimensions
Securing a Motor Control
Center
Anchor bolts (1/2” [13 mm]) may be pre-located and embedded in the
foundation prior to installation. Two bolts per vertical section fasten the motor
control center through its internal mounting angle to the foundation (corner
sections require three bolts and 40” [1016 mm] wide sections require four
bolts). See Figure 2.2 through Figure 2.6 for general dimensions. Dimensions
matching your equipment can be found on the elevation drawings shipped
with your MCC.
HEIGHT OF
HANDLE
6' 7" MAX
FLOOR LINE
CEMENT PAD
Summary of Contents for CENTERLINE
Page 1: ...CENTERLINE Low Voltage Motor Control Centers Instruction Manual ...
Page 6: ...Publication 2100 IN012B EN P April 2005 iv ...
Page 8: ...Publication 2100 IN012B EN P April 2005 vi ...
Page 30: ...Publication 2100 IN012B EN P April 2005 2 10 Installation Procedures ...
Page 42: ...Publication 2100 IN012B EN P April 2005 3 12 Final Checklist Before Energizing ...
Page 48: ...Publication 2100 IN012B EN P April 2005 4 6 Installing Conduit and Cable ...
Page 56: ...Publication 2100 IN012B EN P April 2005 5 8 Installing and Removing Plug In Units ...
Page 68: ...Publication 2100 IN012B EN P April 2005 7 10 Operator Handle and Unit Interlock ...
Page 76: ...Publication 2100 IN012B EN P April 2005 9 6 Maintenance ...
Page 78: ...Publication 2100 IN012B EN P April 2005 10 2 Maintenance After Fault Condition ...
Page 80: ...Publication 2100 IN012B EN P April 2005 11 2 Renewal Parts ...
Page 85: ...Publication 2100 IN012B EN P April 2005 Parts Illustrations 12 5 Notes ...
Page 86: ...Publication 2100 IN012B EN P April 2005 12 6 Parts Illustrations Notes ...