Pre-installation
1.
Inspect the device for shipping damage.
2.
See
Before You Begin on page 7
.
3.
Record the i-Sense monitor serial number.
4.
Register the monitor at
www.igrid.com
.
5.
Configure the monitor hardware for the service voltage.
6.
Configure the communication software using the Ethernet port (this can
be done after installation and power-up).
Environmental Conditions
The monitor is rated for installation in the following environment:
• Indoor use only, no conductive pollution.
• Altitude up to 2000 m (6500 ft).
• Temperature range 0…40 °C (32…104 °F).
• Maximum relative humidity 95%, noncondensing.
Mounting Instructions
• Provide 10 in. (250 mm) clearance around the monitor for cooling and
access.
• Remove the left and right covers (four Phillips screws, two at the top and
two at the bottom).
• Mount the monitor to a vertical surface using the four mounting holes.
Two of the four mounting screws should penetrate into studs at least 1 in.
(25 mm), screws at least 1.5 in. (38 mm) long recommended.
Electrical Connections
1.
Install branch protection: upstream fuse or circuit breaker protection rated
20 A or less is required. Protection rated less than 5 A is not
recommended.
2.
Conduit entry available from the top or bottom.
3.
Connect the Ground (Earth) wire to the #10-32 stud near the bottom
knock-out.
4.
Connect mains line to the INPUT_1 terminal block, according to the
proper wiring diagram from
Table 5
. For the 6-channel version only: if the
INPUT_2 terminal block is present, wire the second 3-phase set using the
same wiring diagram.
WARNING:
Do not apply power to the monitor until the wiring is completed
and right-side cover is replaced. Installation must be performed by an
electrician, in accordance with all local, and national codes.