Site Preparation
7705 SAR-A Chassis Installation Guide
57
The following rack requirements must be met:
•
The rack must be constructed using channel or angle rack uprights that are at least
1.25 in. (3.2 cm) deep and 5 in. (12.7 cm) wide (maximum) (see
•
For seismic applications, the rack must be an approved Seismic Frame.
•
The rail mounting holes in the equipment rack must align with the mounting holes on
the chassis mounting brackets. The 7705 SAR-A mounting brackets are
factory-installed for a NEBS mount in a 19-inch rack.
•
When installed in the rack, the 7705 SAR-A chassis requires a minimum air
movement of 0.5 m/s in order to maintain proper thermal performance up to
149
°
F (65
°
C).
Chassis Location Requirements
Allow at least 1.75 in. (4.4 cm) clearance above and below and at least 2 in. (5.1 cm) clearance
on the sides of the chassis for proper airflow. Allow at least 2.5 in. (6.4 cm) at the front of the
chassis for cable management. The clearances are shown in
and described in
.
Warning:
Failure to comply with the location requirements outlined in
and
may impede proper airflow, which may result in
equipment failure due to overheating.
Summary of Contents for 7705 SAR-A
Page 23: ...Mandatory Regulations 7705 SAR A Chassis Installation Guide 23 Figure 3 Earth ground 9718 ...
Page 66: ...Installation Site Assessment 66 7705 SAR A Chassis Installation Guide ...
Page 76: ...Chassis Ground Wiring 76 7705 SAR A Chassis Installation Guide ...
Page 82: ...Wiring and Connecting DC Power 82 7705 SAR A Chassis Installation Guide ...
Page 132: ...7705 SAR A Ports 132 7705 SAR A Chassis Installation Guide ...
Page 154: ... 2015 Alcatel Lucent All rights reserved 3HE 10141 AAAB TQZZA Edition 01 ...