7
GENERAL WARNINGS
•
ADK 200 cast iron boilers are designed for working with hot water heating
and/or hot water plumbing and produced with the proper technology and
materials suitable to this design.This desing is restricted to use out of it’s
aim of use.
•
ADK 200 boilers are delievered as sections and services assemble the
boilers in the operation area. The assembling of the boiler must be made
by Alarko Carrier technical services. Removing or re-assembling of the
boiler should also be made by licensed Alarko Carrier services, if not the
risk of damage is high.
•
In the assembling of the boiler; there must be a proper and safe concrete
platform for to put the boiler on.
•
In the assembling of the boiler, an empty space must be left from sides
for safety requirements and for future repairing operations.
•
Starting and first operation of the boiler must be made by authorized
Alarko Carrier technicians.
•
Do not add or pump water to the boiler or plumbing system as it is working
and hot. For adding water to the boiler or to the systen please wait for
water temperature to come 40ºC. Circulation pump must surely be started
while adding water to the system. If not, the sections may crack.
•
If the boiler will be kept off for a long time the electric system must be
shut down from the main fuse. The electric must be cut off from the main
shelter/fuse as the boiler is in repair,service or cleaning.
•
In summer months, when the boiler is off for a long term, for preventing
probable problems with circulation pumps, must be started 1 -2 times per
month for 5 minutes (The water with chalk can cause problems if the
pump is not used for long time period).
•
The periodical controls of the boiler and the burner must be done. If not,
the boiler can lose efficiency and the fuel amount used can increase.
•
The capacity choice of the boiler must be made according to the projects
thatprepared properly in the terms of related standards. If not the the
efficiency will be low.
•
ADK 200 boilers are produced for heating only. For heating the sanitary
water another equipment such as water heater or heat exchanger is
needed. And for proper efficiency in this operation, correct water
heater or heat exchanger must be selected.
Summary of Contents for ADK 200
Page 1: ...Operation Manual ADK 200 HEATING SYSTEM CAST IRON BOILERS WITH LIQUID GAS FUEL...
Page 2: ...Kitap Revizyon Tarihi 310706 Kitap Bask Tarihi 310706 Kitap Revizyon No 1...
Page 3: ...ADK 200 HEATING SYSTEM CAST IRON BOILERS WITH LIQUID GAS FUEL Operation Manual...
Page 4: ......
Page 6: ......
Page 12: ...10 ADK 200 CAST IRON BOILER TECNICAL DATA...
Page 13: ...11 ADK 200 CAST IRON BOILER DIMENSIONS...
Page 18: ...16 INSTRUCTIONS ABOUT FLUE...
Page 20: ...18 BOILER CONTROL PANELS...
Page 21: ...19 ELECTRICAL DIAGRAMS...
Page 27: ...25 DIAGRAMS GASSIDERESISTANCE EXITFLUEGASRESISTANCE...