20
5.
Commissioning the RE-46 PROFINET
5.1 Electrical connections
Switch off the fieldbus segment where the RE-46 PROFINET should be installed.
Prepare the power cable (+24V DC) connection, but
do not yet connect
it!
1
POWER cable 24V
2
Fieldbus Port 1
3
Fieldbus Port 2
Connect the
RE-46 PROFINET
with your PROFINET fieldbus network (
see chap-
ter 4.5.1
This can either be done by ready-to-use link cables (recommended) or if necessary
by the use of field mountable connectors and cables.
HINT:
When using field mountable connectors and cables, an electronic cable test
should be applied after the installation to make sure the cabling fulfills the Ether-
net standards and is free of connection failures.
When installing ready-to-use cables, this test is not required.
1
2
3