Unit Lifting - Condenser
General
• Employ lifting specialists
• Local codes and regulations relating to the lifting of this type of equipment should be observed
• Each chain/sling must be capable of lifting the whole unit
• Lift the unit slowly and evenly
IMPORTANT
Only use lifting points provided.
• Do not use 1 chain between 2 lifting points to avoid load shift.
• Ensure that chains/slings DO NOT crush the casework, coil or fan assemblies.
• If the unit is dropped it should immediately be checked for damage and reported to Airedale.
• Airedale will accept no responsibility for mishandling during the positioning of the equipment.
Use 4 lifting eyes attached to 4 individual slings / chains (supplied by others) and attach 1 to the top of each of the 4
corner legs using the holes provided as illustrated.
Installation Data
Vertical Air Discharge
The unit is delivered in horizontal air discharge configuration
(with the mains isolator and fan speed controller already
configured for vertical air discharge) secured to a pallet.
Where possible the unit should be moved with the pallet in
place.
Horizontal Air Discharge
The unit is delivered in horizontal air discharge configuration secured to a pallet.
Where possible the unit should be moved with the pallet in place.
Use 4 lifting eyes attached to 4 individual slings/chains (supplied by others) and
attach 2 to each top leg using the holes provided as illustrated.
Before lifting into final position, the unit legs should be re-orientated, refer to
instructions provided at delivery.
CAUTION
Check the unit is as ordered, discrepancies or transit damage should be reported to Airedale immediately.
CAUTION
Care should be taken to ensure the unit does not sustain damage before it is lifted into final position.