Installation and Maintenance Manual
18
5.
OPERATIONS
Start
‐
up Procedures
CAUTION
Start-up to be conducted by qualified service engineers familiar with equipment.
Ensure that drain lines are fitted to both the dump outlet as well as the overflow outlet (if
necessary).
Ensure drain lines have been charged with water.
Check all duct work connections are clean, and clear of any obstruction. Ensure all relevant
dampers and fire dampers are open or at the correct setting.
Check if there are any signs of excessive vibration on fans.
Ensure filters have been fitted in the outdoor air inlet.
Check that sufficient electrical power is available.
Unit Air Flows
The Supply airflow quantity set point has been pre-set in the factory, allowing the fan to
automatically adjust the speed to meet the required airflow. The airflow setpoint can still be
adjusted using the air volume controller (UNIcon CPG). Please contact the Air Change technical
support team for instructions.