Mounting and commissioning
– English –
FloCo-Top-2
32
6.3
Mounting the product
The permissible ambient temperature must not be exceeded,
see table 1, page 8. This means that you must not mount the
FloCo-Top-2 on top of or next to a non-insulated boiler part,
above opening dampers at furnaces or to the flue gas pipe.
The float housing must point vertically to the top.
1.
Mount FloCo-Top-2 to the boiler casing using the enclosed
bracket 4 self-tapping screws.
You can use the bracket as a template when screwing in the
screws.
2.
Mount the suction line into the female thread G 3/8 of the hous-
ing with a cylindrical screwed pipe connection G 3/8 as per
DIN 3852 (see chapter 10, page 20) or with the
enclosed pipe
connection
(Ø 8/10 mm) and seal it.
Do not use hemp or Teflon tape.
3.
Use a support bushing in the case of soft or semi-soft copper
pipes.
4.
Lock with an open ended spanner size SW 22 and tighten the
screwed connection at the connection piece.
5.
Mount the burner hoses.
Make sure the sealing surfaces are clean and not damaged.
CAUTION
Damage to the pump or the system if the flow and return lines
are not properly connected
Do not confuse the supply and return connections, not even
during commissioning for a short period of time.