28
Fig.14. View of the Data log tab
4.1.7. Once the flow meter has been set up:
- close the device communication channel with PC by pressing the
in
the upper left corner of the Monitor BUF (310) application window;
- close the Monitor BUF (310) application window;
- set the device to WORK mode: remove the jumper from the contact pair
for allowing the modification of service parameters. Seal the contact pair.
4.2. Pre-commissioning
4.2.1. Pre-commissioning shall be performed by representatives of the organi-
zation having the right to perform such works or by representatives of the
manufacturer.
4.2.2. After the installation of the flow meter, the pipeline is filled with the meas-
ured liquid. The flow meter's battery is connected, the flow meter is con-
nected to the computer and adjusted in accordance with the instructions
in section 4.1 of this manual.
4.2.3. The flow meter is ready for operation on initial start-up or after a long
interruption in operation after:
- A 30-minute flushing of the CP with fluid stream
- A 30-minute warm-up of the flow meter.
4.2.4. When commissioning the flow meter, check:
- The correct connection of the flow meter and the interacting equipment
according to the selected connection diagram
- The correctness of the set operating modes of the flow meter's universal
and logic outputs.
After commissioning, the SMC enclosure can be sealed to protect
against unauthorized access during operation.