Temperature Control Units : Sentra with VE Series Instrument
Page: 25
Advantage Engineering, Inc.
525 East Stop 18 Road Greenwood, Indiana 46142
317-887-0729 Fax: 317-881-1277
Service Department Fax: 317-885-8683
www.AdvantageEngineering.com
Some older models have overload relay where a red button that pops out if the
overloads are tripped. Simply push the button in until the overloads are reset.
Other overload relays have a switch. This switch will be positioned with the
indicator pointing up when in normal operation. The indicator will be pointing to
the left when the overloads are tripped. To reset, simply turn the switch to where
the indicator points up.
3.
If a motor overload situation persists, the operator must adjust the flow rate to
match the system pressure loss (reduce flow rate) to prevent continual tripping of
the overload relay. This procedure is outlined here:
a.
Open electrical cabinet panel door. The panel cover is hinged and held
open by a support cable. Note that the electrical power is engaged at
this point and caution must be observed while the cabinet panel is
open.
b.
Identify the motor starter block. This block
consists of the motor starter contactor
and the overload relay.
c.
Place an amp meter on a single power
lead coming from the overload relay.
d.
Locate the motor name plate on the
pump motor housing. The full load amp
rating for the motor is listed on the name
plate.
e.
Engage the electrical power supply and start the unit.
f.
The amp meter will display the motor amps. Compare the actual motor
amps as displayed on the amp meter to the full load amp rating as listed
on the motor name plate.
g.
If the amp draw is excessive (higher than the listed name plate amp
rating), a throttling valve must be installed in the “from process” water
Pump Motor Controller
Normal Operating Position
Tripped Position
WARNING: Electrical power is engaged and caution should be employed while the cabinet is
open.
Summary of Contents for Sentra SK Series
Page 2: ......
Page 6: ...Page 6 THIS PAGE INTENTIONALLY BLANK ...
Page 20: ...Page 20 THIS PAGE INTENTIONALLY BLANK ...
Page 30: ...Page 30 THIS PAGE INTENTIONALLY BLANK ...
Page 36: ...Page 36 THIS PAGE INTENTIONALLY BLANK ...
Page 68: ...Page 68 THIS PAGE INTENTIONALLY BLANK ...
Page 69: ...END 2017 ADVANTAGE ENGINEERING INC RE 01272017 ...
Page 70: ......