Modifications reserved
Page 12/50
3.3.2
Optional sea freight packaging (wooden box)
Perform the following steps to unpack the UPS equipment from the sea freight package:
1.
Disassemble the wooden box by removing all screws.
2.
Remove the plastic film and bag from the UPS, by cutting it without causing damage to the cabinet;
the edges are not protected.
3.
Remove the accessories form its location, see Figure 8 on the next page. The std. set of
accessories is: user manual, 2x painted sockets, screws, 4x feet and keys.
4.
Tear out the 2x humidity-absorber. One is inside the front part of the UPS: open the door using the
keys and then tear out the absorber. The other one is at the back as shown in Figure 9 (next page)
5.
Follow the steps 5) - 7) of the previous section 3.3.1.
1)
2)
Figure 7: Photograph and 3D drawing of PowerWave 33 S3 with sea freight packaging.
Summary of Contents for PowerWave 33 Series 3
Page 1: ... Copyright 2017 ABB All rights reserved User Manual PowerWave 33 Series 3 60 120 kW ...
Page 46: ...Modifications reserved Page 46 50 10 Attachments 10 1 Technical data sheet ...
Page 48: ......
Page 49: ... Copyright 2016 ABB All rights reserved Technical data sheet PowerWave 33 Serie 3 60 120 kW ...