Commissioning
6.1
Commissioning requirement
To commission the device, a PC with ETS is required along with a connection to the ABB i-bus
®
, e.g. via a
KNX interface.
Once the bus and auxiliary voltages are connected, the device is ready for operation.
6.2
Commissioning overview
The ABA/S 1.2.1 Logic Controller is commissioned using the
Logic Controller/*
application.
Note
* … = Current version number of the application. Please refer to the software information on our
homepage for this.
ETS is required in order to parametrize the device.
For information on how to use the i-bus
®
Tool, see 4.5
Integration in the i-bus® Tool
6.3
Assignment of the physical address
The physical address, group address and parameters are assigned and programmed in ETS.
The device features a
Programming
button for physical address assignment. The red
Programming
LED
lights up after the button has been pressed. It goes off once ETS has assigned the physical address or the
Programming
button is pressed again.
The device performs an ETS reset during physical address programming. This resets all states.
Summary of Contents for i-bus KNX ABA/S 1.2.1
Page 1: ... PRODUCT MANUAL ABB i bus KNX ABA S 1 2 1 Logic Controller ...
Page 2: ......
Page 6: ......
Page 20: ......
Page 106: ......
Page 108: ......
Page 112: ......
Page 114: ...ABB i bus KNX Appendix 114 2CDC509086D0201 ABA S 1 2 1 13 2 Notes ...
Page 115: ...ABB i bus KNX Appendix ABA S 1 2 1 2CDC509086D0201 115 Notes ...