10
Installation and maintenance guide
1ZSC000563-AAX EN, REV. A, 2019-03-21
Voltage tap
The voltage tap is available as an option, instead of the test tap.
The bushing has a voltage tap that is connected to the second outermost conductive layer of the condenser
core. The voltage tap is used to measure the bushing insulation by capacitance and dissipation factor. The
cover connects the outermost conductive layer to ground, and must always be installed when the bushing is
energized.
The maximum one minute test voltage for this voltage tap is 2 kV
rms
. The voltage tap can be used as a power
source, if it is connected to an external capacitance. The operating voltage is limited to 6 kV.
CAUTION!
Do not energize the bushing without a test adapter or the cover installed. The cover connects the
outermost conductive layer to ground and will prevent damage to the bushing.
G000388
1
Stud
2
Cover
3
Grounding spring
4
O-ring
Test adapter, 2769 522-C, optional equipment
The test adapter 2769 522-C is available for permanent connection to measuring circuits. Please refer to Test
adapter – Installation and maintenance guide 1ZSC000563-ACD.
G004198
Summary of Contents for GSC Series
Page 40: ...40 Installation and maintenance guide 1ZSC000563 AAX EN REV A 2019 03 21 ...
Page 46: ...46 Installation and maintenance guide 1ZSC000563 AAX EN REV A 2019 03 21 ...
Page 48: ...48 Installation and maintenance guide 1ZSC000563 AAX EN REV A 2019 03 21 ...
Page 52: ...52 Installation and maintenance guide 1ZSC000563 AAX EN REV A 2019 03 21 ...