Installation and maintenance guide
1ZSC000563-AAX EN, REV. A, 2019-03-21
49
7 Re-packing
7.1 Re-packing of the bushing
Overview
G004181
Procedure
1.
Install the transport container (1):
1.
Replace the drying agent in the transport
container (1).
2.
Install the gasket (2).
3.
Carefully put the transport container on the
bushing, and install the bolts.
CAUTION!
Make sure that the transport container
does not cause damage to the
condenser core.
NOTE!
The transport container has to be
ordered separately.
G004199
Torque
50 Nm
2.
Lift the bushing. Refer to
Lifting the bushing out of the transport box,
page
Summary of Contents for GSC 200
Page 40: ...40 Installation and maintenance guide 1ZSC000563 AAX EN REV A 2019 03 21 ...
Page 46: ...46 Installation and maintenance guide 1ZSC000563 AAX EN REV A 2019 03 21 ...
Page 48: ...48 Installation and maintenance guide 1ZSC000563 AAX EN REV A 2019 03 21 ...
Page 52: ...52 Installation and maintenance guide 1ZSC000563 AAX EN REV A 2019 03 21 ...