Installation checklist
69
Installation checklist
Checklist
Check the mechanical and electrical installation of the drive before start-up. Go
through the checklist below together with another person. Read the
on the first pages of this manual before you work on the unit.
Check
MECHANICAL INSTALLATION
The ambient operating conditions are allowable. (See
Mechanical installation, Technical data
:
.)
The unit is fastened properly to the cabinet. (See
and
)
The cooling air will flow freely.
The motor and the driven equipment are ready for start. (See
ELECTRICAL INSTALLATION
(See
Planning the electrical installation, Electrical installation.
)
The VAR (frames A and B) and EMC/VAR1/VAR2 (frames C and D) screws are removed if
the drive is connected to an IT (ungrounded) supply network.
The capacitors are reformed if stored over one year (ask local ABB representative for more
information).
The drive is grounded properly.
The supply (input power) voltage matches the drive nominal input voltage.
The supply (input power) is connected to U1/V1/W1 (UDC+/UDC- in case of a DC supply)
and the terminals are tightened to specified torque.
Appropriate supply (input power) fuses and disconnector are installed.
The motor is connected to U2/V2/W2, and the terminals are tightened to specified torque.
The braking resistor (if present) is connected to R+/R-, and the terminals are tightened to
specified torque.
The motor cable (and braking resistor cable, if present) is routed away from other cables.
There are no power factor compensation capacitors in the motor cable.
The external control connections to the JCU Control Unit are OK.
There are no tools, foreign objects or dust from drilling inside the drive.
Summary of Contents for ACS850 series
Page 1: ...ACS850 Hardware Manual ACS850 04 Drive Modules 1 1 to 45 kW...
Page 2: ......
Page 4: ......
Page 14: ...Table of contents 14...
Page 20: ...About this manual 20...
Page 32: ...Planning the cabinet assembly 32...
Page 38: ...Mechanical installation 38...
Page 48: ...Planning the electrical installation 48...
Page 50: ...Electrical installation 50 1 2 3 4 5...
Page 68: ...Electrical installation 68...
Page 76: ...Maintenance 76...
Page 102: ...du dt and common mode filtering 102...
Page 108: ...Dimension drawings 108 Frame size A...
Page 109: ...Dimension drawings 109 Frame size B...
Page 110: ...Dimension drawings 110 Frame size C...
Page 111: ...Dimension drawings 111 Frame size D...
Page 113: ...Dimension drawings 113 EMC filters type JFI x1 JFI A1...
Page 114: ...Dimension drawings 114 JFI B1...
Page 115: ...Dimension drawings 115 EMC filters type JFI 0x...
Page 117: ...Dimension drawings 117 Braking resistors type JBR xx...