07 COMMISSIONING
3BHS799208 E01 REV E
ACS5000 WATER-COOLED
USER MANUAL
122/186
7.6.6
Motor checklist
1) Motor is installed, aligned and alignment protocol available.
□
2) Motor is not coupled to driven load.
□
3) Grounding is completed
□
4) Motor auxiliaries (eg, bearing lubrication) are ready
□
5) Control and monitoring signals are connected.
□
7.6.7
Insulation tests checklist
1) Insulation of the cables to input transformer, from input
transformer to drive and from drive to motor is tested, and
measured values within required limits.
□
2) Test report is available
If the commissioning personnel carry out the test, an additional
day per drive-motor combination must be reserved. After the
test, the mains cables can be connected, except at the drive end.
Test must comply with the specification.
□
7.6.8
Power checklist
1) Medium voltage available for startup of drive.
□
2) Low voltage is available for startup of drive.
□
7.6.9
Miscellaneous checklist
1) Sufficient number and correct type of spare parts available
□
2) Sufficient quantity of deionized water according is available.
(see “Appendix C – Mechanical drawings”).
□
3) Air conditioning of drive room ready for load run of drive
□
4) Optional equipment (eg, chiller) ready
□