up Procedure – Single Cooling ( Cubb) 

1.

ONLY once the condenser has been hardwired and copper piping  
connected can the cooling system be turned on.

2.

Insert cooling system IEC plug (orange cable) into the cooling system 
socket at the rear of switchboard labelled (Cooling system).

3.

Ensure switchboard is powered and both the Cooling System RCD 
and Cooling System are in the 

ON position 

4.

Start-up cooling system on remote located at the back door on 

left hand side

.

5.

Press the 

START

 button on the cooling system remote. 

6.

Ensure temperature is set to 23° on cooling mode and FAN 
STRENGTH is on HIGH.

7.

Installation complete

5.6 Start

 

up Procedure – Dual Cooling ( Cubb) 

1.

ONLY once the condensers have been hardwired and copper piping  
been connected can the cooling system be turned on.

2.

Insert cooling system (IEC) plugs (Orange cable) into:

3.

Plug Orange Cable (Labelled – Cooling system 1) into Permanent 
supply 1

4.

Plug Orange Cable (Labelled – Cooling system 2) into Permanent 
supply 2

5.

Ensure switchboard is powered and both the Cooling System RCD 
and Cooling System are in the 

ON position 

6.

Start-up cooling system on remote located at the back door on 

left hand side.

7.

Press the 

START

 button on the cooling system remote. 

8.

Ensure temperature is set to 23° on cooling mode and FAN 
STRENGTH is on HIGH.

9.

Run both system together for 5 minutes – ensure both systems are 
operating.

10.

Pull out both plugs without turning cooling system off from the 
permanent supply and plug into Cooling systems 1 & 2  outlets.

11.

One system will be operation following this step.

12.

Installation complete

 

 

 

 

 

Zellabox 

Safety

 

Instructions 

  

  

  

  

  

 

7

Name of Parts

Remote Controller

Signal transmitter

Receiver

To use the remote controller, aim the 

transmitter at the indoor unit. If there 
is anything to block signals between 
the unit and the remote controller, 
such as a curtain, the unit will not 
operate.
Do not drop the remote controller. Do 

not get it wet.
The maximum distance for 

communication is approx. 7m.

FAN setting button

It selects the air

 ow rate setting. 

 

 Page 14

POWERFUL button

POWERFUL operation. 

 Page 17

Display (LCD)

It displays the current settings.

(In this illustration, each section is 
shown with all its displays on for the 
purpose of explanation.)

TEMPERATURE 
adjustment buttons

It changes the temperature setting.

 

 Page 12

ON/OFF button

Press this button once to start 

operation.
Press once again to stop it. 

 Page 11

Front cover

Open the front cover. 

 Page 8

HEAT PUMP model

ARC452A4

COOLING ONLY model

ARC452A13

01_EN_3P291209-1.indd   7

01_EN_3P291209-1.indd   7

12/8/2011   9:18:00 PM

12/8/2011   9:18:00 PM

 

Mechanical Diagram

Model Number: PX3-5092R-F8

4

Cooling Remote

C

o

o

lin

g

 Syst

e

1

C

o

o

lin

g

 Syst

e

2

Pe

rma

n

e

n

Su

p

p

ly 

1

Pe

rma

n

e

n

Su

p

p

ly 

2

5 Single & Dual cooling

 

system

 

commissioning

 

steps:

13

Содержание Cubb

Страница 1: ...1 Zellabox Installation Manual...

Страница 2: ...mmissioning Reference for air conditioning contractor 5 1 Condenser 5 2 Commissioning 5 3 Wiring 5 4 Copper Piping 5 5 Start up Single Cooling 5 6 Start up Dual Cooling 6 Online Access PDView Access O...

Страница 3: ...ta storage equipment The facility in the form of a cabinet has a host of built in features which ensure that your server is secure accessible and fully portable The Micro Data Centre can accommodate y...

Страница 4: ...ote Caution needs to be taken when removing the side panels of the Micro Data Centre in particular when dealing with the 38U as they are heavy We recommend a 2 man lift when removing and re installing...

Страница 5: ...ED ELECTRICAL CONTRACTOR WITH THE NECESSARY TRAINING Zellabox Safety Instructions 3 1 Power Supply requirements Zellabox 3 2 Switchboard Operation Following the connection to mains power DEPENDING ON...

Страница 6: ...6 Zellabox Safety Instructions 3 Power connection 3 3 Power Supply diagram to PDU switchboard 12U Cubb only Cooling system RCD Mains power Cooling system UPS Power Non monitored sockets...

Страница 7: ...View FRONT VIEW ISOLATOR MAIN 3KVA UPS 6KVA UPS AVAILABLE POWER P ROT E CT I ON NO RCD DIVERTER SURGE 3 8 T O T AL C U T O U T 47 TOTAL CUT OUT 485 NOMINAL 19 INCH RACK CASE 10 1 8 1 8 1 8 1 8 RCD COO...

Страница 8: ...door is opened by the push button located inside the Zellabox See user manual for programming options Use card reader until you are ready for biometric access mode 4 3 L E D Key Pad Operation The defa...

Страница 9: ...issioning Once the Zellabox has been positioned in its proposed location and connected to power the air conditioning contractor can commission the cooling system Only once the air conditioning contact...

Страница 10: ...ble termination in condenser 4 core cable 1 Red Brown 2 Blue 3 White Green Earth 5 3 Wiring cont Electrical Hazard Ensure cooling system is in the OFF position on Zellabox base mounted switchboard and...

Страница 11: ...tem commissioning steps PLEASE NOTE WHEN PLUGGING THE CABLE CONNECTORS YOU SHOULD HEAR A CLICK TO CONFIRM CONTACT AFTER INSERTING THE PLUG ENSURE BOTH ORANGE AND GREY CABLES ARE LOCKED BY TURNING THE...

Страница 12: ...ape to keep dirt or water out Be sure to place a cap Rain Liquid pipe Inter unit wiring 2 Remove burrs with the cut surface facing downward so that the chips do not enter the pipe 3 Put the flare nut...

Страница 13: ...mode and FAN STRENGTH is on HIGH 9 Run both system together for 5 minutes ensure both systems are operating 10 Pull out both plugs without turning cooling system off from the permanent supply and plug...

Страница 14: ...ower case Z numeral 3 lower case L sign lower case B lower case O and lower case X c Accept the terms of use check box d Once connected to the PDU the following similar image should appear 4 Access th...

Страница 15: ...o OPTION 1 Press enter Use the following to access Login admin Password z3ll box Accept the terms of use check box OPTION 3 To access the Zellabox PDU through a network switch or something similar fol...

Страница 16: ...these steps Assign the desired IP address to the PDU by referring to OPTION 1 above Plug network cable switch directly into the PDU Access the PDU through local Display If you have any questions plea...

Страница 17: ...e next few slides Please note Accidental discharge will occur if this guide is not followed step by step For effective and safe installation follow the steps below Please note Accidental discharge wil...

Страница 18: ...nister to the Pyrorack by inserting the plug and tightening the washer 5 Reinsert the canister back into the Pyroack 6 Place the Pyrorack into position top of the Zellabox 7 3 Commissioning Steps 1 Fi...

Страница 19: ...1 and 2 by pressing the isolate zones buttons located on the front panel 3 A beeping sound will continue intermittently as a reminder 4 Once you have completed work within the MDC and you are ready t...

Страница 20: ...Warning Fire Suppression System Information 20...

Страница 21: ...issioning steps 7 7 Important tips Before working within the Zellabox ALWAYS ensure you follow these steps 1 Turn key switch to manual 2 Isolate both zones 1 and 2 by pressing the isolate zones button...

Страница 22: ...sted in the cooling system section as this will overheat the equipment The Zellabox Micro Data Centre is a PLUG N PLAY unit therefore once it has been installed by a qualified contractor the Micro Dat...

Страница 23: ...Zellabox Zellabox Pty Ltd PO Box 1035 Osborne Park DC Western Australia 6916 AUSTRALIA 1300 117 644 www zellabox com info zellabox com Version 2014 011 23...

Отзывы: