Install-MONTE_BASE - SEP_2015.doc www.yunca.co.nz
Page 2 of 4
MONTE BASE WOODBURNER
– TYPICAL FLUE INSTALLATION
(drawings on the following pages not drawn to scale)
FIG A MONTE BASE WOODBURNER Flue Mounted Shield
(STD Flue Guard) Kit Installation
Complies (with heater) to AS/NZS 2918:2001
CEI LI NG PLATE
2 5 m m m in . BET WEEN LI NER & ANY TI MBER
ENLARGEMENT OF CEI LI NG ASSEMBLY
3 0
0
3 0 0 m m Sq. T I MBER FRAME
TIMBER RAILS
SUPPORT ANGLES
LINER POSITIONED BY SPIDER
BRACKETS. TOP/BOTTOM
INSULATION BOUNDARY SHIELD
CUT CEI LI NG MAT ERI AL
BACK 2 5 m m CLEAR
OF BOUNDARY SHEI LD.
CEI LI NG
2 5
3 0
0
CONDITIONS FOR FLUES
(Refer Fig. E)
1.
The FLUE shall extend to:
Not less than 600mm above the highest
point on the roof if within 3.0m of that point,
or
Not less than 1000mm above the
intersection point with the roof and not lower
than any point of the roof within 3.0m.
In any case the length of the flue shall not be
less than 4.6m from the ash floor protector.
In some situations the Local Council may
vary the above requirements.
2.
The flue system must be tested and comply
with AS/NZS2918:2001, Appendix F.
3.
The insulation boundary shield shall be
capable of preventing accidental migration of
loose-fill or any combustible material by any
action of wind or by persons moving in the
ceiling space.
FIG B.
These instructions spare parts information,
operation and maintenance guides may be
downloaded from www.yunca.co.nz
FIG B
Ash floor Protector
10mm GAP BETWEEN
TOP PLATE LIP AND
U/SIDE FLUE GUARD