YORK INTERNATIONAL
55
FORM 150.62-NM1
G
3. Program/verify the Cooling Setpoints, Program
Setpoints, and unit Options. Record the values
below (see sections on Setpoints and Unit keys
for programming instruction).
G
4. Put the unit into Service Mode (as described un-
der the Control Service And Troubleshooting sec-
tion) and cycle each condenser fan to ensure
proper rotation.
G
5. Prior to this step, turn system 2 off (if applicable -
refer to Option 2 under “Unit Keys” section for
more information on system switches.) Connect
a manifold gauge to system 1 suction and dis-
charge service valves.
Place the Unit Switch in the control panel to the
ON position. As each compressor cycles on,
ensure that the discharge pressure rises and
the suction pressure decreases. If this does
not occur, the compressor being tested is oper-
ating in the reverse direction and must be cor-
rected. After verifying proper compressor rotation,
turn the Unit Switch to “OFF.”
The chilled liquid setpoint may need
to be temporarily lowered to ensure all
compressors cycle “on.”
This unit uses scroll compressors
which can only operate in one direc-
tion. Failure to observe these steps
could lead to compressor failure.
G
6. YCAL0040 - YCAL0080 units only – Turn system
1 off and system 2 on (refer to Option 2 under
“Unit Keys” section for more information on sys-
tem switches.)
Place the Unit Switch in the control panel to the
ON position. As each compressor cycles “on,”
ensure that the discharge pressure rises and
the suction pressure decreases. If this does
not occur, the compressor being tested is oper-
ating in the reverse direction and must be cor-
rected. After verifying proper compressor rotation,
turn the Unit Switch to “OFF.”
The chilled liquid setpoint may need
to be temporarily lowered to ensure all
compressors cycle “on.”
G
7. After verifying compressor rotation, return the Unit
Switch to the off position and ensure that both
Systems are programmed for “ON” (refer to Op-
tion 2 under “Unit Keys” section for more infor-
mation on system switches).
INITIAL START-UP
After the preceding checks have been completed and
the control panel has been programmed as required in
the pre-startup checklist, the chiller may be placed into
operation.
G
1. Place the Unit Switch in the control panel to the
ON position.
G
2. The first compressor will start and a flow of re-
frigerant will be noted in the sight glass. After sev-
eral minutes of operation, the vapor in the sight
glass will clear and there should be a solid col-
umn of liquid when the TXV stabilizes.
G
3. Allow the compressor to run a short time, being
ready to stop it immediately if any unusual noise
or adverse conditions develop.
G
4. Check the system operating parameters. Do this
by selecting various displays such as pressures
and temperatures and comparing these readings
to pressures and temperatures taken with mani-
fold gauges and temperature sensors.
G
5. With an ammeter, verify that each phase of the
condenser fans and compressors are within the
RLA as listed under Electrical Data.
CHECKING SUPERHEAT AND SUBCOOLING
The subcooling and superheat should always be
checked when charging the system with refrigerant.
When the refrigerant charge is correct, there will be no
vapor in the liquid sight glass with the system operating
under full load conditions, and there will be 15°F (8.34°C)
subcooled liquid leaving the condenser.
An overcharged system should be guarded against. The
temperature of the liquid refrigerant out of the condenser
should be no more than 15°F (8.34°C) subcooled at
design conditions.
1
Содержание YCAL0080SC
Страница 112: ...YORK INTERNATIONAL 112 ELEMENTARY DIAGRAM YCAL0014SC YCAL0030SC FIG 11 ELEMENTARY DIAGRAM Wiring Diagrams...
Страница 114: ...YORK INTERNATIONAL 114 ELEMENTARY DIAGRAM YCAL0014SC YCAL0030SC LD03532 FIG 12 ELEMENTARY DIAGRAM Wiring Diagrams...
Страница 115: ...YORK INTERNATIONAL 115 FORM 150 62 NM1 This page intentionally left blank 4...
Страница 116: ...YORK INTERNATIONAL 116 ELEMENTARY DIAGRAM YCAL0034SC FIG 13 ELEMENTARY DIAGRAM Wiring Diagrams...
Страница 117: ...YORK INTERNATIONAL 117 FORM 150 62 NM1 FIG 13 ELEMENTARY DIAGRAM Cont d LD03533 ELEMENTARY DIAGRAM YCAL0034SC 4...
Страница 118: ...YORK INTERNATIONAL 118 FIG 14 ELEMENTARY DIAGRAM ELEMENTARY DIAGRAM YCAL0034SC LD03534 Wiring Diagrams...
Страница 119: ...YORK INTERNATIONAL 119 FORM 150 62 NM1 This page intentionally left blank 4...
Страница 120: ...YORK INTERNATIONAL 120 ELEMENTARY DIAGRAM YCAL0040SC YCAL0060SC FIG 15 ELEMENTARY DIAGRAM Wiring Diagrams...
Страница 122: ...YORK INTERNATIONAL 122 ELEMENTARY DIAGRAM YCAL0040SC YCAL0060SC FIG 16 ELEMENTARY DIAGRAM Wiring Diagrams...
Страница 124: ...YORK INTERNATIONAL 124 ELEMENTARY DIAGRAM YCAL0064SC YCAL0080SC FIG 17 ELEMENTARY DIAGRAM Wiring Diagrams...
Страница 126: ...YORK INTERNATIONAL 126 ELEMENTARY DIAGRAM YCAL0064SC YCAL0080SC FIG 18 ELEMENTARY DIAGRAM Wiring Diagrams...
Страница 130: ...APPENDIX 1 DIMENSIONS FIG 19 TYPE CP 1 FIG 20 TYPE CP 2 LD03839 LD03840 Appendix 1 Isolators...
Страница 135: ...YORK INTERNATIONAL 135 FORM 150 62 NM1 This page intentionally left blank...