7
OPM-108/B
PREPARING THE UNIT
START-UP CHECK LIST
A Start-Up Completion & Warranty Validation Form was
sent along with this manual. This must be completed and
returned to WINCO Inc. within 180 days of the factory
invoice date.
If this form is not returned, the Warranty may be voided.
UNPACKING
1. As you receive your unit, it is critical to check it for any
damage. If any damage is noted, it is always easiest to
refuse the shipment and let WINCO take care of the
freight claim. If you sign for the unit, the transfer of the
ownership requires that you file the freight claim
2. Before proceeding with the preparations of your new
generator for operation, take a couple of minutes to
ensure the unit you have received is the correct model
and review the specification pages in this manual to
ensure that this unit meets your job requirements.
CAUTION: EQUIPMENT DAMAGE:
These units are shipped with oil and a 50/50 mix of coolant.
Be sure to check all fluid levels before operating. See engine
manufacturer’s instruction manual for recommended oil
requirements before initial starting.
Once generator set is on-site:
1. Carefully remove the crate.
2. After inspecting the engine-generator for external,
physical damage, locate and check the following items
packed with the unit:
a. Installation and Operator’s Manual.
b. Engine manufacturer’s instruction manual.
c. Start-up and warranty validation form.
d. Battery hold-down brackets & hardware.
e. Unit components or accessory items shipped loose
for on-site installation.
f. Optional accessories.
3. Remove main frame hold-down bolts.
4. Unit can now be lifted from shipping rails.
LIFTING THE GENERATOR SET
NOTICE: PERSONAL INJURY:
To prevent injury to persons or equipment, observe the
following guidelines when lifting the generator:
Due to the different designs, configurations, options,
weights, site conditions, and available material handling
equipment, specific lifting instructions are not provided for
each individual generator set model. General guidelines
provided are applicable to the entire generator line. It
is the responsibility of the installing party to follow the
lifting equipment’s operator’s manual to prevent injury to
personnel and damage to the generator. Smaller generator
sets may not require use of overhead lifting equipment and
may be placed on the pad with basic material handling
equipment, i.e. a forklift.
CAUTION:
Do not attempt to lift the generator set by the means of
the lifting eyes on the engine or generator end. These
lifting points are only for the use during the manufacturing
process and are designed for lifting of the individual
generator set components.
WARNING:
NEVER attempt to lift the fuel tank filled with fuel. Sloshing
of the fuel can cause a shift in the balance of the fuel tank,
making for a DANGEROUS, unbalanced lifting load. If the
generator was shipped on the fuel tank, use the lifting
points located on the fuel tank to move the entire generator
set into place. DO NOT PLACE FUEL IN THE TANK PRIOR
TO LIFTING.
INSTALLATION
WARNING: PERSONAL INJURY:
PERSONAL INJURY - Before proceeding with the
installation, be sure the DSE7310 is in the “stop” position.
Before proceeding with the installation, be sure the
Generator MLCB (Main Line Circuit Breaker) is in the ‘OFF’
position and the unit starting battery is disconnected.
GENERAL INFORMATION
This engine-generator set is generally supplied as weather
enclosed packages for quick installation on an outdoor
concrete pad. They are also available as open skid mounted
units for indoor installation in a building or protective
enclosure, properly ventilated, supplied by the installer. The
factory weather enclosures are acoustical housing intended
for outdoor installation only. Factory weather enclosed
units are not intended to be used indoors and no support is
available to assist in re-engineering finished packaged units.
All versions must be bolted to a solid base for proper
operation. A properly designed concrete pad is necessary
for stationary operation. A substantial DOT certified trailer
is required for mobile applications. Consult a qualified,
licensed electrician or contractor to install and wire the gen-
set. The installation must comply with all national, state, and
local codes.
Before beginning the installation process, recheck the
voltage, phase, and amperage rating of the generator
set. Be certain it can handle the intended load and are
compatible with the intended loads. Plans for installation
should be prepared with proper attention to mechanical
and electrical engineering detail to assure a satisfactory
system installation.
The information in this manual is offered only as a guide to
finalizing your installation plans.
NOTICE:
For full service switching of the entire load, the ATS must be
‘SE’ (Service Entrance) rated or must have a properly rated
fusible disconnect installed before the ATS to protect the
contacts.