
S
TILETTO
AL
O
PERATING
I
NSTRUCTIONS
2-24
Original Instructions
TP-5418901-F
August 2020
2.8 Test the Installation
Follow all precautions while testing the Mast System installation.
Equipment Damage!
Verify that a power source capable of delivering the specified Mast
System voltage and current has been properly connected to the Control Box.
Polarity!
Ensure the electrical mains polarity is correct before initializing the Mast System.
To test the installation:
1. Review the Pre-Operation Check (Section 3.1).
2. Prepare the Mast System for operation.
3. Extend the mast.
4. Lower the mast.
See Section 3 for additional details on these procedures.
Содержание 711990491
Страница 2: ......
Страница 46: ...STILETTO AL OPERATING INSTRUCTIONS 1 32 Original Instructions TP 5418901 F August 2020 ...
Страница 98: ...STILETTO AL OPERATING INSTRUCTIONS 7 2 Original Instructions TP 5418901 F August 2020 ...
Страница 114: ...STILETTO AL OPERATING INSTRUCTIONS 9 4 Original Instructions TP 5418901 F August 2020 ...