WhisperGen PPS16 Installation and Commissioning Manual Rev: 080801
35
21. Completing commissioning and filling
out the commissioning checklist.
To complete the commissioning procedure:
1.
Start the WhisperGen and record the second StartFuel1 value at the end of the
commissioning checklist.
There will be a slight difference between the two values.
2.
Complete the Commissioning Details section at the back of the User’s Manual.
3. Complete the Commissioning Checklist in the Installation and Commissioning manual
and return it to the Whisper Tech Limited and the distributor.