Receiver Installation
The lift installer must fit
the receiver. The
receiver mounts to three
threaded studs at the
top of the PCB tray
using M4 nylon insert
nuts and plain washers
supplied in the fixing
boxes.
The receiver loom
connects to PLK on the
main PCB (see Fig. 3).
Figure 3: Receiver installation
Wireless Call Station Looms
Wireless Call Station Looms are
15-way Molex shorting plugs that
replace the hard-wired call station
looms ‘stop’ circuit. Two are
required for each lift. Ensure the
mains power is off. Connect the
wireless call station looms into the
two call station sockets on the right
hand side of the PSU PCB (see
Fig. 4).
Note:
If hard-wired call stations are
fitted also, then the wireless call
station looms are not used.
Connect the call station looms in
the usual manner.
Figure 4: PSU PCB showing both Wireless Call Station Looms connected.
Set-up
On the main PCB, move dip switch
SW3 A
to the lower position to enable
the stop button on wireless handsets.
Leave dip switch
SW4 A
in the upper
position for both manual and power
doors. This enables the door lock
solenoid to release for both door types
(see Fig. 5).