Receiver Installation 

The lift installer must fit 
the receiver. The 
receiver mounts to three 
threaded studs at the 
top of the PCB tray 
using M4 nylon insert 
nuts and plain washers 
supplied in the fixing 
boxes. 
 
The receiver loom 
connects to PLK on the 
main PCB (see Fig. 3). 
 

 

Figure 3: Receiver installation 

 

 
 

Wireless Call Station Looms 

Wireless Call Station Looms are 
15-way Molex shorting plugs that 
replace the hard-wired call station 
looms ‘stop’ circuit. Two are 
required for each lift. Ensure the 
mains power is off. Connect the 
wireless call station looms into the 
two call station sockets on the right 
hand side of the PSU PCB (see 
Fig. 4). 
 

Note:

 If hard-wired call stations are 

fitted also, then the wireless call 
station looms are not used. 
Connect the call station looms in 
the usual manner. 
 

 

 

 

Figure 4: PSU PCB showing both Wireless Call Station Looms connected. 

 

 
Set-up 

 
On the main PCB, move dip switch 

SW3 A

 to the lower position to enable 

the stop button on wireless handsets. 
 
Leave dip switch 

SW4 A

 in the upper 

position for both manual and power 
doors. This enables the door lock 
solenoid to release for both door types 
(see Fig. 5). 
 

 

 
 

Figure 5: Dip switch setting 

 

 
 