1

C

ALIBRATION 

P

ROCEDURE FOR 

DTS-2077

T

IME 

M

EASUREMENT 

S

YSTEM

Equipment Required:

1

Frequency counter with high stability time base (9½ digit resolution)

1

Digital voltmeter (6½ digit resolution)

1

Variable output power supply (Ø-6 VDC)

3

50 ohm SMA connectorized cables of equal length (approximately
1 meter)

1

5/64" Hex wrench

1

Straight blade screwdriver, medium

1

Small, non-conductive straight blade screwdriver tool for
adjusting oscillator

1

DTS-2077 User's Guide

4

SMA shorting caps provided with the system

A/R

Connector adapters as required to interface listed equipment
with SMA cables

1

Oscilloscope with 1 GHz minimum bandwidth

1

Calibrated delay line with SMA interconnects

1

Function generator with outputs to 100 KHz and a variable duty
cycle adjustment (pulse width).

1

Computer with GPIB interface and cable

1

“Virtual Instruments” -or- calibration software

Notes:

1)

Use only electronic test equipment with calibrations traceable to NIST standards.

2)

Refer to the DTS-2077 User’s Guide for general operating instructions.

3)

For all measurements using the DTS-2077, the system’s cover should be installed and
the system should be allowed to warm-up at least 15 minutes.

4)

All calibration operations should be made at a grounded workstation while wearing
a grounded strap.

1.0

Removal of the System Top and Bottom Covers

(1-1)

Place the system on a sturdy horizontal surface such as a workbench.  The system should
be resting on all four feet.  Verify the AC power cord is not connected at this time.

(1-2)

Using the Hex wrench, remove (3) screws from the left and (3) screws from the right side
panels.  Then remove (15) screws from the top side.

(1-3)

While slightly spreading the side panels from the bottom, lift the cover straight up until
clear of the system.  Store cover and screws in a safe place.

(1-4)

Turn DTS system over, so the top is resting on the workbench, and the bottom cover is
facing up.

Содержание DTS-2077

Страница 1: ...Calibration Procedure for the DTS 2077 Time Measurement System WAVECREST Corporation...

Страница 2: ...utine expression of that philosophy For this reason any current WAVECREST product may differ in some respect from its published description but will always equal or exceed the original design specific...

Страница 3: ...s 2 Reference Voltage Check 3 3 0 100MHz Oscillator Check 4 4 0 Self Calibration 4 5 0 Reference Voltage Operational Check 5 6 0 Calibration Signal Outputs 5 7 0 AC Performance Checks 6 8 0 Arming and...

Страница 4: ...cable 1 Virtual Instruments or calibration software Notes 1 Use only electronic test equipment with calibrations traceable to NIST standards 2 Refer to the DTS 2077 User s Guide for general operating...

Страница 5: ...ower Supply Checks 2 1 Verify the AC power cord is connected to an appropriate power source 110V 60 Hz or 230V 50 Hz Turn on the main power switch at the rear of the system Then turn on the standby sw...

Страница 6: ...DTS as shown in Figure 1B Verify the voltage is 5VDC 0 05V If adjustment is required both 5VDC modules must be alternately adjusted at VOUT The two 5VDC modules provide load sharing and must be balan...

Страница 7: ...internal calibration sequence by pushing the INT CAL button on the front panel The display will indicate the time remaining to accomplish the internal calibration counting down on the display When th...

Страница 8: ...lower readings on the DTS display It may be necessary to measure and set the DC voltage at the DTS input connectors using a T adapter 6 0 Calibration Signal Outputs 6 1 Using the frequency counter an...

Страница 9: ...s its calibration sequence the DTS will display CALIBRATED The previous mode and display then returns 7 2 Go to Menu 11 see Figure 2 6 in the User s Guide and place the cursor on the CLEAR field Then...

Страница 10: ...the front panel and press FUNC Verify the displayed measurement is 5000 psec 10 psec with JITTER 6 psec 8 3 Set the function generator to output a square wave with a 5 nsec wide duty cycle and a 1V pk...

Страница 11: ...ndby switch on the front panel and the main power switch on the rear of the instrument Remove all cables and unplug the AC power cord from the power source and package the accessories that accompanied...

Страница 12: ...ke Road Edina MN 55439 Yes please include me when you distribute future new versions of the DTS 2077 Calibration Procedure NAME __________________________________________________________ COMPANY _____...

Страница 13: ...adquarters West Coast Office 7275 Bush Lake Road 1735 Technology Drive Suite 400 Edina MN 55439 San Jose CA 95110 612 831 0030 408 436 9000 FAX 612 831 4474 FAX 408 436 9001 Toll Free 1 800 733 7128 1...

Отзывы: