Figure 30 

Exhaust gas discharge through the building chimney and fresh intake from the building chimney with split flue sets

Attention:

 The minimum usable diameter must not 

be under 80 mm or equivalent for the vertical duct 

supplying the combustion air.

Attention:

 

a)  nominal working combustion product temperature : > 70°C max conditions 
b) overheat combustion products temperature : 105° C
c)  the minimum length of the specified connecting ducts; 1 mt / maximum length of the specified 

connecting ducts; 10 mt

d) For size/shape of the end of the fitting please refer 2.2.14. Installation with Vertical Flue Sets page 13, 

Fig.26.

e) Please re adjust TsP Paramater P22 = Flues gas pipe length ( value 1 = 1 meter ) according to actual flue 

lenght

f) Its MUST to use NON RETURN valve ON the flue gas system. 
g) non-return valve function has to be checked annually by authorised service.

Information for the design of the common duct system for a type C(10) boiler

a)  The boiler is designed to become connected to a common duct system that is designed to operate 

where the static pressure in the common flue duct might exceed the static pressure in the common air 

duct by 25 Pa under the condition that n-1 boilers are running at maximum nominal heat input (Qn,max) 

and 1 boiler at the minimum heat input allowed by the controls

b) combustion product mass flow rate at maximum nominal heat input are given technical table.
c)  combustion product mass flow rate at minimum heat input allowed by the controls are given technical 

table.

d) G20 : CO2 or O2 content of the combustion products at nominal operating conditions 9 % ( +0,5/-0,5 ) 

G30 / G31 : CO2-content; 10.00 % ( tolerance : +%0,5 / -0,5 % )

e) minimum allowable pressure difference between combustion product outlet and air inlet shall be 

declared as -200 Pa (including -100 Pa wind pressure).

General for connection of a type C(10) boiler to a common duct system

Characteristics and the applications of the common duct system to which the boiler can be connected, 

with at least the following information:
a)  the flue duct system shall be CE marked and comply with EN 15502 standart 12.2.1.4.111.2;
b) nominal combustion products temperature for dimensioning the common duct system shall be 

declared as 25 °C;

c)  the combustion product mass flow rate at maximum heat input shall be specified for every connection 

point; the terminal of the common duct shall be designed to induce a draft;

d) condensate flow into the boiler is allowed;
e) maximum allowable recirculation rate of 10 % under wind conditions;
f) the maximum allowable pressure difference between combustion product inlet and air outlet of the 

common duct system shall not be exceeded when n-1 boilers are running at maximum nominal heat 

input (Qn,max) and 1 boiler at the minimum heat input allowed by the controls;

g) the common flue duct shall be appropriate for an overpressure of at least 200 Pa;
h) the duct system shall not include a draft diverter.

Warning:

  the boiler if it is installed as a C (10) boiler  and IF / when the boiler is disconnected the air 

outlet and the combustion product inlet openings shall be closed and checked on tightness. 

C

No place of the output flue should be blocked and not prevent other 
connections. If the output pipe passes 1000 mm nearby of a plastic or painted 
groove or 500 mm of painted fringes, an aluminium shield with at least 1000 
mm length should be placed below the groove or fringe. Output pipe should 
be at least 2 m over surfaces those may be reached by individuals.

Under certain weather conditions, output pipe may emit water vapour;
installation should not be performed at places where this vapour may cause 
discomfort.

Exhaust gases should be prevented from entering flue ventilation spaces.

Flue system of combi may be installed from inside the room without requiring 
intervention from the external wall. For that reason, a housing should be 
installed in the wall for lining the internal surface of channel wherein the 
output pipe passes through the wall, particularly for thick walls.

C

10

Figure 31 

Gas appliance with combustion air supply and flue gas 

discharge designed for connection to an air/flue system.

Separate ducts are used here for combustion air supply and flue gas discharge, 

ensuring that every appliance is supplied with fresh combustion air. Air/flue systems 

of this type are on the market with both parallel and concentric duct configurations.
Appliances with either concentric or parallel air/flue system 

can be connected to both configurations. 

C

43

Содержание EWA 20

Страница 1: ...CONDENSING COMBI BOILER INSTALLATION MANUAL EWA 20 EWA 24...

Страница 2: ...EWA 20 EWA 24...

Страница 3: ...n Case of Using Bottled Gas 9 Filling the siphon for Condensation Line 10 Installation at Partially Protected Exteriors 10 Electrical Connections 10 Optional Controls Room Thermostat Outside Sensor an...

Страница 4: ...4 warmhaus com...

Страница 5: ...ilable BE FR YES II 2H3B P Natural Gas 20 mbar G20 Available AT CH CY CZ DK EE FI GR IT LT NO RO SE SI SK YES II 2E3B P Natural Gas 20 mbar G20 Available DE YES II 2ELL3B P Natural Gas 20 mbar G20 Ava...

Страница 6: ...6 warmhaus com...

Страница 7: ...Figure 2 User s Guide Figure 5 Exhaust gas flue set 471 1000 GAS G3 4 G3 4 G3 4 80 mm 65 mm 65 mm 64 mm 725 mm 592 mm 422 mm G1 2 G1 2 75 mm 73 mm 110 m m 114 mm OPTIONAL Ewa Priwa ERP Priwa ERP Plus...

Страница 8: ...r semi full brick wall according to installation scheme and with connection screws and not to be used for other purposes In case of using different materials for installation combi shall be out of the...

Страница 9: ...1 2 7 In Case of Using LPG Tank LPG use is recommended for heat requirements over 24 kW New LPG stock tanks may contain settled gas residues nitrogen however that pauperises the mixture assigned to t...

Страница 10: ...able to use gas and water connection pipes for earthing WARMHAUS A cannot be held as responsible for any damages and losses on individuals or commodities arising from failing to provide earth connecti...

Страница 11: ...nsor is activated when connected as independent from the used room thermostat typology and functions as common with room thermostats The relation between installation input temperature and exterior we...

Страница 12: ...0 600021 WT RF03 Large Screen Modulated Weekly Program Scheduled Wireless room thermostat Product code 153 11 660 600022 150 cm Min 30 cm Room thermostat shall be mounted 1 25 to 1 5 m above the groun...

Страница 13: ...d in the hot tap water Hydrophore should be used if required Prior to filling the radiator installation it must be flushed and all wastes must be cleaned Warning In order to prevent invalidity of devi...

Страница 14: ...mum 3 storey buildings Drainage and Ventilation Pipe Min 19 mm Water Air proof insulation Figure 2 26 Connection of condensate Drainage Pipe to External Soil Vent Stack Connection of Condensate Draina...

Страница 15: ...thorized service appointment request Gas opening approval certificate should be taken from the local gas company for your gas line Combi electricity connection should be made via 2 or 3 Amps fuse Figu...

Страница 16: ...o be used in exhaust gas installation of hermetic combi should be original Warmhaus flue sets and they should be used by considering measurements and restrictions given in installation instructions In...

Страница 17: ...ontent 10 00 tolerance 0 5 0 5 maximum allowable draught and maximum allowable pressure difference between combustion air inlet and flue gas outlet including wind pressures 120 Pa characteristics and...

Страница 18: ...temperature for dimensioning the common duct system shall be declared as 25 C c the combustion product mass flow rate at maximum heat input shall be specified for every connection point the terminal...

Страница 19: ...H C R A I J K I L S B T U Likely flue positions requiring a flue terminal guard Figure 32 Environmental locations of flue Terminal Position with Minimum Distance mm A1 Directly below an opening air br...

Страница 20: ...tion hatch edge must not be fitted more than 1 5 meters away from a flue joint Inspection hatches should be fitted at every change of direction Flue Data 60 100mm Concentric flue systems information W...

Страница 21: ...ceed 10 m with single elbow horizontally Also this total length reduces by 1 m with every 90 elbows or two 45 elbows Maximum 3 pieces of 90 elbow can be used a Standard Flue Set Elbow 90 b Flue Extens...

Страница 22: ...es Flue Data WARNING Warmhaus flue pipe technical specification Vertical Termination Maximum length 11 meters including the bend or adaptor connected directly to the boiler Effective flue length for t...

Страница 23: ...al flue set installation application Implementation L1 0 3 m L2 0 5 m 45 elbow equivalent length L3 2 0 m L4 0 5 m 45 elbow equivalent length L5 1 0 m L6 1 5 m L Total 6 3 m 6 3 m Lmax 11 m Correct in...

Страница 24: ...ension of 140 mm see Table 1 It must not be sited above the flue pipe The flue and air pipes must extend by at least 40 mm from the wall surface Condensing boiler emit a visible plume of water vapour...

Страница 25: ...0 Condensing Flue Extension L 1000 mm 15311660600015 White 60 100 Condensing Flue Extension L 2000 mm 15311660600016 White 60 100 Condensing 45 Elbow 15311660600017 White 60 100 Condensing 90 Elbow L...

Страница 26: ...0 mm 80 mm L 500 mm 153 11 660 600091 80 Condensing Twin Flue Extension Pipe L 1000 mm 80 mm L 1000 mm 153 11 660 600092 80 Condensing Twin Flue Extension Pipe L 2000 mm 80 mm L 2000 mm 153 11 660 600...

Страница 27: ...n products will not cause a nuisance and that the terminal will not obstruct the passageway 3 If a terminal is less than 2 metres above a balcony above ground or above a at roof to which people have a...

Страница 28: ...NTC 4 Check cabling and connectors between double NTC and board 5 Reset Restart boiler E 06 No ignition Boiler does not work E06 error code flashing on the screen Gas supply failure 1 RESET boiler che...

Страница 29: ...ault Boiler does not work E12 error code flashing on the screen Domestic heating water temperature sensor in storage tank faulty 1 Check intermittent contacts or open contacts on harness carefully 2 C...

Страница 30: ...ed 2 Check the root cause of Error code to solve 3 If fault still persists call for authorised service E 37 Low voltage anomaly Boiler does not work E37 error code flashing on the screen Low voltage 1...

Страница 31: ...onnections Combustion calibration Electronic board Gas valve failiure 1 Call for authorised service at first 2 Check gas supply pressure must be 20 17 mbar Gas pressure must be in between on this valu...

Страница 32: ...ulation flue gas leak from flue gas path to fresh air side check flue gas sealings specially 5 Check any problems on the ionisation electrode like condensation rust etc and control poistioning of the...

Страница 33: ...e electrode 5 Check for condensation on the cabling AND OR on board 6 Check earth connection between board and electrode 7 Check electrode cabeling between board and electrode 8 Check combustion CO2 o...

Страница 34: ...sed service must perform Au To calibration E 96 Flue or air suction way blockage Boiler does not work E96 error code flashing on the screen Blokage on flue Blokage on air suction path 1 Call for autho...

Страница 35: ...omestic Hot Water Circuit Water Heating Energy Efficiency Class A A A Water Heating Declared Load Profile XL L XL Water Heating Energy Efficiency 85 81 84 Gas Consumption at Maximum m h 2 47 2 83 0 73...

Страница 36: ...Heating Energy Efficiency s 91 92 92 Useful efficiency at rated heat output and high temperature regime 2 4 87 60 87 57 87 57 Useful efficiency at 30 of rated heat output and low temperature regime 1...

Страница 37: ...arefully prepared but we reserve the right to make changes and improvements in our products which may affect the accuracy of the information contained in this leaflet All goods are sold subject to our...

Страница 38: ...EWA 20 EWA 24 CONDENSING COMBI BOILER INSTALL ATION MANUALEwa Installation Service Manual Code 15011606000140 Revision Date R00 12 2021...