5.3 Procedure
Follow the points below in the order given:
First determine where the individual components are to be installed. Refer to
the specifications in this chapter and in the sensor and switch actuator data
sheets.
Adhere to the maximum line lengths.
Do not use lines of a larger cross-section than specified.
Then determine which cables are required to connect the components with
one another. Use the instructions given in
Chapter 6 on page 34
.
Lay the required lines. Preferably use cable ducts to route the motor lines.
WARNING
Electrical operating equipment must be mounted for easy access
(VDE0100).
Install and wire the individual components.
Check the wiring before switching on the power supply to the control.
Then commission the unit. Only then will the control be ready to use. The
steps required for commissioning are explained in detail in these instructions.
Check the correct running direction of the sun shading products by operating
the "Up" and "Down" buttons on the control.
Check that the connected sensors are functioning properly.
Check that the readings displayed in the Start menu for the temperature
and brightness are plausible.
Check that the wind speed reading changes when the vane is turned.
Check whether precipitation is detected (moisten the sensor surface with
water).
Then adjust the functioning of the system to the ambient conditions and
special requirements. Use the operating instructions as a guide as well.
Chapter 11 ab Seite 104
of these instructions contains a table with all avail-
able setup steps (parameters), their limit values and the factory settings.
If you change the factory settings, enter the new values of the unit into the
table after completing the work.