8.The equipment is ready for use after the
electrical wire and fuel hose have been con-
nected.
INSTRUCTIONS FOR INSTALLATION IN
THE DUCT
1.Cut the hoses, insulating channels and pro-
tecting plates so that they each the inner sur-
face of the duct.
2.Fasten the hoses to the heater by using
clamps. The exhaust pipe must be tightened
properly by using power press binding.
3.Mount the heater to its place.
4.Tighten the joint between the exhaust pipe
and the duct by using acrylic mass.
5.The equipment is ready for use after the
electrical wire and fuel hose have been con-
nected.
N.B. When taking the combustion air from un-
der the floor, make sure that the base floor has
sufficient ventilation. Install a protective spiral
at the end of the hose.
- In a high (over 5 metres) and large (cross-
sectional surface over 15 x 15 cm) duct, ex-
haust gases are cooled down so that the
moisture in them is condensed, thus causing
the chimney to decay, as well as decreasing
the draught. Therefore, a brick duct should
be lined with stainless steel pipe (diameter
50-70 mm), as well as filling the space bet-
ween the pipe and duct by, for example, ex-
panded clay.
- Air for fire ventilation cannot be taken from
the same duct through which exhaust gases
are discharged.
INSTRUCTIONS FOR INSTALLATION
THROUGH THE WALL
1.Install the covering plates on the wall and tigh-
ten the joint by acrylic mass. Put a plate with
8 holes on the outer wall.
2.Cut the ducts and insulating channels as
shown in fig. 6 (items A and B).
ACut them so that the insulation will be 10
mm outside the wall (the insulating plate
shall also be 10 mm outside the wall).
BCut them so that the ducts will be 40-45
mm outside the wall.
3.Fasten the ducts to the heater by using hose
clamps. The exhaust gas pipe must be tigh-
tened properly by using power press binding.
4.Mount the heater and its ducts to their pla-
ces.
5.Mount the insulating channels and protecti-
ve plate from the outside. Cut small tongues
on one of the protective plates (Fig. 6, item
C) and install this one with the tongues
against the covering plate on the outer wall.
6.Install the exhaust gas discharge casing and
the shroud (protection against contact) so
that the pipe ends reach the limit stops of the
casing. Tighten the joint between the casing
and covering plate by using acrylic mass.
7.Fasten the heater on the floor or foundation
casing by screws.
INSTALLATION INSTRUCTIONS
Fig. 6.
Covering plate
Insulating plate
Covering plate
Insulating
channels
Hose
clamps
Discharge casing
Shroud (protection
against contact)
T0209