10TA Service Manual
SERVICE OPERATIONS
4/28/14
9-18
Component Removal and Replacement Operations
Cutter Motor
The cutter motor’s bearings are prelubricated and sealed and require no further
lubrication. If the motor needs replacing, proceed as follows:
1.
Turn power off and lockout disconnect.
2.
Check terminals with voltmeter to confirm power is off.
3.
Remove motor terminal cover and disconnect wires. Mark wires for ease of replacement.
4.
Remove four cap screws around the motor flange and separate the motor from the reducer. Watch
for shaft key that must be reinstalled later.
5.
Check the motor electrically to confirm it is defective.
6.
Apply Anti-Seize lubricant to the shaft of the replacement motor.
7.
Position the shaft key in the motor keyway, align it with the reducer keyway and install the motor.
Make sure the key stays in position as shaft is inserted.
8.
Install the four cap screws to hold the motor in place on the reducer.
9.
Connect the wires and install the terminal cover.
10.
Check motor rotation to make sure the cutter turns in the proper direction. Reverse two wires at
the motor if necessary to change rotation direction.
Cutter Gear Reducer
To remove the gear reducer, proceed as follows: (See FIGURE 9-16)
1.
Turn power off and lockout disconnect.
2.
Remove motor from reducer.
3.
Loosen (slightly) the four bolts and nuts holding the gear reducer in place.
4.
Remove the four bolts holding the mounting plate to the water tank gear enclosure and remove the
reducer and mounting plate from the tank.
5.
Measure the distance between the top of drive gear and the mounting plate for future reference.
6.
Remove the three cap screws from the gear and hub and install two 1/4”-20 x 2” long all thread set
or cap screws in the threaded holes of the drive gear. These two screws can be used as jacking
bolts to remove the gear from the tapered split hub.
7.
The split hub can be removed by driving a screwdriver in the split and sliding the hub off the shaft.
8.
The new gear reducer can then be installed by reversing the removal procedure.
9.
Be sure the gear and hub is properly positioned on the shaft so it will have a full vertical mesh with
the cutter ring gear.
10.
Final gear meshing should be adjusted so there is only a slight amount of play between the ring
gear and drive.
11.
Make sure all bolts are tightened securely and there is no excessive gear noise when the cutter
motor is running.
Содержание P18FXT
Страница 4: ...Vogt Tube Ice Machines Installation Service Manual and Parts Catalog 12A4171M08 10TA Model ...
Страница 10: ...10TA Service Manual TABLE OF CONTENTS vi BLANK ...
Страница 20: ...10TA Service Manual INTRODUCTION 4 14 14 1 10 BLANK ...
Страница 40: ...10TA Service Manual INSTALLING YOUR TUBE ICE MACHINE 4 14 14 3 18 BLANK PAGE ...
Страница 43: ...10TA Service Manual HOW YOUR TUBE ICE MACHINE WORKS 4 14 2014 4 3 FIGURE 4 1 Water Cooled Piping Schematic ...
Страница 44: ...10TA Service Manual HOW YOUR TUBE ICE MACHINE WORKS 4 14 2014 4 4 FIGURE 4 2 Air Cooled Piping Schematic ...
Страница 50: ...10TA Service Manual START UP AND OPERATION 4 14 14 5 6 BLANK ...
Страница 51: ...10TA Service Manual ELECTRICAL CONTROLS 4 14 14 6 1 6 Electrical Controls FIGURE 6 1 Control Panel SS PB1 PB2 ...
Страница 52: ...10TA Service Manual ELECTRICAL CONTROLS 4 14 14 6 2 FIGURE 6 2 Control Panel Components Standard ...
Страница 60: ...10TA Service Manual ELECTRICAL CONTROLS 4 14 14 6 10 BLANK ...
Страница 111: ...10TA Service Manual 10 7 OPTIONS AND ACCESSORIES FIGURE 10 4 Wiring Schematic Mid Size Machine P112 P118 P18XT ...
Страница 112: ...10 8 10TA Service Manual OPTIONS AND ACCESSORIES BLANK ...
Страница 120: ...10TA Service Manual TABLES CHARTS 7 2 14 11 8 BLANK ...
Страница 124: ...10TA Service Manual INDEX 5 30 14 12 4 ...