Detailed view of concrete-lined finished floor
1260
1360
L1 + 200
B
A
C
C
A
Agitator centre
B
Concrete block out (for recessed installation)
Section C - C
A
630
630
1260
> 330
50
30
A
Agitator centre
Installation information for intermediate floors
■ Design the support structure of the intermediate floor to ensure
that the weight of the fuel does not bear on the screw trough.
■ Build the intermediate floor after installing the discharge.
■ Ensure that the intermediate floor incl. substructure is at the same
level as the screw trough.
■ The leaf spring bundles must be able to rotate without touching the
intermediate floor. Observe the minimum clearance.
■ Take into account any hatches required for maintenance and
inspection.
Discharge screw conveyor AH to horizontal discharge AH
For part no., see pricelist
The arms of the horizontal discharge move the fuel into the conveyor
channel inside the fuel store. The conveyor channel is open inside
the fuel store and sealed outside the fuel store.
Standard delivery:
■ Conveyor channel running through the entire system with specially
adapted discharge screw conveyor
Note
Article price per m
Max. discharge screw conveyor AH length = 10 m
Total price = total length h in m x unit price
Additional discharge screw conveyor AH, per m
For part no., see pricelist
For two-boiler discharge systems with a total system output of up to
1440 kW. Extension possible up to 10 m. Conveyor channel running
through the entire system with specially adapted discharge screw
conveyor.
Fuel discharge
(cont.)
48
Viesmann
VITOFLEX 300-UF
5
5682428