During the mounting on the floor, the drain is integrated into the floor
construction. At the same time, it can e. g. be integrated into the level-
ling screed or heat insulation. If necessary, a vertical drainpipe can be
led through a drill hole in the floor at the same time.
NOTICE!
The creation of a floor recess must be agreed with the fol-
lowing people:
– a structural engineer
– the on-site fire protection inspector or the specialist
engineer for fire protection
If necessary, proof of compliance with building code or an
expert's report must exist.
2.4.2
Sealing
The drain can be sealed both conventionally as well as with bonded
sealing.
Depending on the type of sealing, you will require the relevant equip-
ment set
Ä
Chapter 2.5 „Required accessories“ on page 13.
Mounting on a floor
Fig. 3: General mounting example – Mounting
on the floor