Vertiv™ NetSure™ ITS 12V DC Power Shelf Installation & User Manual
23
6
Installing SCC Controller and Rectifier Modules
NOTE!
Install SCC controller and rectifier modules as directed in the “Initially Starting the
System” procedure starting on
page 24.
For SCC controller installation instructions, refer to SCC Controller Instructions (UM1M520HNA).
For rectifier module installation instructions, refer to rectifier module Instructions (UM1R123000)..
7
Initially Starting, Configuring, and Checking System
Operation
7.1
Important Safety Instructions
CAUTION!
Performing various steps in the following procedures may cause a service interruption and/or result in the
extension of alarms. Notify any appropriate personnel before starting these procedures. Also, notify personnel when these
procedures are completed.
7.2
Initial Startup Preparation
•
Ensure that all blocks, except the last one, in the “Installation Acceptance Checklist” starting on page 2 have been checked.
•
If the system was integrated into an Open Compute IT Rack and shipped to its final destination with rectifiers pre-installed,
REMOVE THE SHIPPING SUPPORT BRACKET BEFORE POWERING THE SYSTEM. See
Figure 7-1:
Removing Shipping Support Bracket
Front
P/N 561578
(Open Compute Rack
Shipping Support Bracket)