Vertiv™ NetSure™ ITS 12V DC Power Shelf Installation & User Manual
3
•
This product is intended to be installed in a data center facility and be connected to a MESH-bonding network (MESH-BN)
or to the common bonding network in a network telecommunication facility (CO, vault, hut, or other environmentally
controlled electronic equipment enclosure).
•
This system is suitable for installation as part of the Common Bonding Network (CBN) or a data center building MESH-
bonding network (MESH-BN).
•
The installer should be familiar with the installation requirements and techniques to be used in mounting the module
mounting assembly(s) onto the mounting rails of an IT rack.
•
Rectifier module and module mounting assembly ventilating openings must not be blocked and temperature of air entering
these must not exceed rated operating ambient temperature range found in SAG588706100.
•
Clearance requirements are:
a)
Recommended minimum space clearance for the front of each module mounting assembly is 80 mm (3 inches).
b)
Recommended minimum space clearance for the rear of each module mounting assembly is 80 mm (3 inches).
c)
Module mounting assemblies may be stacked together, with no space between them.
4.2
Inspecting the Equipment and Storing for Delayed Installations
4.2.1
Inspecting the Equipment
General
Compare the contents of the shipment with the bill of lading. Report any missing items to the carrier and your local Vertiv
representative immediately.
While the system is still on the truck, inspect the equipment and shipping container(s) for any signs of damage or mishandling.
As the equipment is moved off the truck and unpacked, visually examine the system for transit damage.
Do not attempt to install the system if damage is apparent.
If any damage is noted, file a damage claim with the shipping agency within 24 hours and contact Vertiv to inform them of the damage
claim and the condition of the equipment.
4.3
Securing the Module Mounting Assembly(s) to the Mounting Rails of an IT
Rack
Install the module mounting assembly(s) into a 19” mounting frame of an IT rack as follows.
P/N SXK2310021/1 Mounting Rail Kit Procedure
Refer to
1.
Install P/N SXK2310021/1 rack mounting rail kit onto the frames of an Open Compute IT rack (version 1 rack).
2.
Slide the module mounting assembly into the front of the IT rack, resting the bottom of the module mounting assembly on
the mounting rails installed in the IT rack.
3.
Secure the front mounting flanges to the IT rack with the furnished cage nuts and screws.