Installation Considerations
NOTE!
If holes are drilled into the exterior of this enclosure and not filled using a seal tight connector, the manufacturer’s
warranty will be void.
5.1
Installation Overview
The following is the recommended sequence for the installation and start-up procedures. The sequence may change according to job
and site conditions.
•
Ensure all site drawings and approvals are in place.
•
Obtain the recommended tools and test equipment.
•
Read “Important Safety Instructions” starting on page vi carefully.
•
Check that all the equipment and materials have been delivered.
•
Proceed with the physical installation of the enclosure.
•
Install circuit breakers inside the enclosure.
•
Install and verify enclosure grounding cable.
•
Connect and verify RRH (Remote Radio Head) cables.
•
Connect and verify alarm and LVD (Low Voltage Disconnect) cables.
•
Connect and verify fiber cables.
•
Connect and verify DC input power cables.
•
Turn-up the system.
5.2
Tools, Test Equipment, and Materials Recommended for Installation
The following tools, test equipment, and materials are recommended for the physical installation of the enclosure:
•
Approved voltage detector.
•
T-handle hex w/pin security tool to open/close enclosure front door.
•
Digital multimeter (DMM), 0 to 200 VDC, 0 to 300 VAC.
•
Torque wrench.
•
Ratchet drive, extensions, sockets.
•
Carpenter’s level.
•
Lineman’s scissors.
•
Lineman’s strippers.
•
Lineman’s cutters.
•
Appropriate crimping tool with dies.