Mechanical Installation
Vertiv | Liebert CRD10 | User Manual
26
Chapter 3: Mechanical Installation
To achieve optimum performance and prolong product life, proper installation is important. In this section, the
mechanical installation will be discussed in detail to help the personnel with the installation process. Before
proceeding with the mechanical installation, the following 3.1 installation notes need to be considered.
3.1
Installation Note
s
1.
Prior to installation, ensure that the installation preparations have been carefully read and implemented
as
per the requirement (refer to section 2.6 on ‘Installation Preparation’ fo
r the details). Check if any
modifications are made to the plumbing, wiring, or ventilation facility before mounting the equipment.
After considering the installation preparations, proceed to the next step in the installation process and
finally set up the system.
2.
The CRD10 is designed as a split system. The indoor unit must be installed on the floor of the equipment
room or computer room. The outdoor unit must be installed outdoors or on the floor of the other rooms
as per the building architecture.
3.
Industry-wide standards are followed for the selection, layout, and fixing of pipes.
4.
During the design and installation process, various factors such as pressure drop, compressor oil return,
noise reduction, and vibration must be considered.
5.
When installing the equipment, follow the design drawings strictly. Reserve space as per the
maintenance and serviceability instructions in the Chapter 2, sec
tion ‘Installation Preparation’. The
manufacturing engineering dimension drawings must be taken as a reference while installing the
equipment.
3.2
System Arrangement during Installation
The general arrangement of the CRD10 air cooled AC unit is shown in Figure 3-1, and the Table 3-1 shows the
calibration of safety components.