Orient the kit supplied front mounting bracket as shown in Figure 5. Note that the bracket comes preassembled with
mounting hardware. Secure the front bracket to the left and right brackets by tightening the captive fasteners. Torque
hardware as show in Figure 5.
Figure 5 Installing Front Mounting Bracket (23-inch distribution cabinet shown, 19-inch distribution cabinet similar)
[ ] 12.
Remove the kit supplied distribution position label (see Figure 6) from the kit supplied storage pouch and (using the
label on the front door as a guide) record the distribution positions onto the kit supplied label.
[ ] 13.
Place the kit supplied distribution position label (see Figure 6) back into the kit supplied storage pouch or remove the
backing from the label and adhere it to a suitable surface near the power system. If the kit supplied distribution position
label is placed back into the storage pouch, remove the backing from the hook-and-loop fastener factory attached to the
storage pouch and adhere the storage pouch to a suitable surface near the power system.
Kit Supplied Front
Mounting Bracket
Torque to
9.6 in-lbs.
Torque to
9.6 in-lbs.
19-Inch / 23-Inch Distribution Cabinet
1-Row Cabinet (shown, 2-row similar)
2-Row Cabinet (BOTTOM ROW Only )
Components removed in
illustration for clarity only.
Installed View