Vertiv | VE Series Rack | User Manual
Installation Instructions
Chapter 3: Installation Instructions
This chapter introduces the installation of each part of the rack. Before installing, ensure that the installation tools and
accessories are in place, and then follow the contents of this chapter. To adjust the relevant parts of the rack, refer to
the installation instructions of the corresponding parts for more information.
•
When installing, wear gloves to keep the rack surface clean.
•
Do not scratch the rack surface during installation.
•
Pay attention to personal safety during installation.
3.1.
Adjusting the EIA Rails
EIA Rail Installation at Factory Mounting Location
The factory mounting position of the EIA rail is shown in
Table 3-1
, and the distance between the two EIA rail sets can be
adjusted according to the equipment requirements.
Table 3-1 Factory Mounting Position of the EIA Rail
Rack Width (W) x
Depth (D) (mm)
Distance between front rail
and inner surface of front
door panel (mm)
Front and Rear Rail
Spacing (mm)
600 x 1100
87.5
734
600 x 1200
87.5
734
800 x 1100
225
634
800 x 1200
225
734
Adjusting the EIA Rail
The EIA rails are divided into left rail and right rail. Please confirm the silkscreen of L and R on the bottom of the EIA
rails before the installation. The diagonal rail structure of the rack is identical. The EIA rail adjustment method is
suitable for 600mm and 800mm wide rack.
The adjustment steps for EIA rails are as follows:
1.
As shown in
Figure 3-1
, use a screwdriver to loosen four M5 combination screws (2200mm height rack with three
adjusting fixtures and six M5 combination screws for reference), move the right front EIA rail from position A
(factory mounting position) to position B (user desired position), use M5 combination screws to lock the EIA rails.