17
SIDE VENTING AND ADDITIONAL INSTRUCTIONS
These additional instructions cover the additional installation requirements for the side
venting version of the Fanfare. These instructions must be read in conjunction with the
main installation and users instructions that are contained within.
GENERAL REQUIREMENTS
1
The citing and configuration of the flue ducting will normally have to be predetermined
before installation commences. The various lengths of duct, elbows and brackets should
be included in a separate kit of parts from the supplier. Ensure all the components
required for the installation are available.
2
The appliance requires a depth of 130mm for fitting which may be achieved by using
either a deep rebated mantel or a false chimney breast. (See Figure 17 and 18)
3
There must be a minimum of 25mm clearance between the flue duct and any
combustible material. The fixing brackets are designed to provide both the method of
supporting the lengths of flue duct and setting the 25mm clearance required.
4
The flue duct may exit from either the left or right of the appliance. The maximum
lengths permissible are shown in the table below. The blanking plate must always be
fixed to the outlet that is not being used.
Number of bends
Maximum length
NONE
7 Metres
1
6.5 Metres
2
6 Metres
3
5.5Metres
4
5 Metres
5
The standard starter duct is 500mm long which is sufficient for hearth widths up to
1220mm (48"). Where a wider hearth is fitted a
longer starter duct (1000mm)
should be used.
FIGURE 17
FIGURE 18