GLT-299-7-2(3) Rev.0
Mar 23, 2018
11
S = 50 ft. (15 m) 2/3 S = 33 ft. (10 m) 1/2 S = 25 ft. (8 m) 1/3 S = 17 ft. (5 m)
Figure 10: Heat detector spacing
— beam construction (plan view)
Notes:
• Detectors can be installed on the bottom of beams when the beams are less than 30 cm (12 in.)
deep and beam spacing is less than 2.4 m (8 ft.).
• Beams less than 20 cm (8 in.) deep are considered flat ceilings. Heat detectors must be installed on
the bottom of the beams.
• Spacing of beams deeper than 20 cm (8 in.) must be reduced by 1/3 of the listed spacing.